Project Duration
Stipulated Date of Commencement
August 29 2013
Stipulated Date of Completion /
Likely Date of Completion November 28 2013
Likely Date of Completion November 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,981,123.00
Awarded for
₹ 39,849,990.00
Contractors
M/s. Concept Creators
Consultants
M/s. Technogem Consultants Pvt. Ltd.