Project Duration
Stipulated Date of Commencement
May 19 2021
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,353,667.00
Awarded for
₹ 2,326,669.00
Project highlights
Furniture works
Contractors
M/s. Creation Interior Contractors
Consultants
M/s. Pankaj Joshi Consultant