Project Duration
Stipulated Date of Commencement
January 25 2019
Stipulated Date of Completion /
Likely Date of Completion April 24 2019
Likely Date of Completion April 24 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 62,31,102.33.
Awarded for
₹ 5,177,777.00
Project highlights
Interior and Furniture Work
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Pankaj Joshi Consultants