Project Duration
Stipulated Date of Commencement
January 25 2019
Stipulated Date of Completion /
Likely Date of Completion April 24 2019
Likely Date of Completion April 24 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 62,31,102.33.
Awarded for
₹ 5,177,777.00
Project highlights
Interior and Furniture Work
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Pankaj Joshi Consultants
See Similar Projects
Supply, Installation, Testing & Commissioning of CCTV system at Goa Medical College.
View Project
Ancillary civil works at Kala Academy and INOX, Panaji, Goa for IFFI 2012.
View Project
Supply, installation, testing & commissioning of C1287 RMU
View Project