Project Duration
Stipulated Date of Commencement January 02 2017
Stipulated Date of Completion /
Likely Date of Completion
July 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 42,824,134.00
Awarded for ₹ 38,640,483.88

Project highlights

Upgraded offie premises for GSIDC in EDC House

 
Gallery Image
Contractors
M/s. Mahendra Relators & Infrastructure Pvt.Ltd
Gallery Image
Consultants
M/s. Intrinsic Classics,
 
Similar Projects

See Similar Projects

Similar Project

Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.

View Project
Similar Project

Igreja De Nossa Senhora de Ajuda Church Ribandar- Balance Civil, Electrical & Miscellaenous works

View Project
Similar Project

Construction of new building for SCERT at Porvorim, Goa – Miscellaneous HT Tapping works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.