Project Duration
Stipulated Date of Commencement August 20 2014
Stipulated Date of Completion /
Likely Date of Completion
November 19 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 60,002,811.80
Awarded for ₹ 54,000,000.00

Project highlights

Temporary office premises for GSIDC office and the District & Sessions Court untill the permanent premises is ready to be occupied.

 
Gallery Image
Contractors
M/s. Knchan Associates,
Gallery Image
Consultants
M/s. Ameet Sukhthankar Architect,
 
Similar Projects

See Similar Projects

Similar Project

Additional works for new SCERT building at Porvorim, Goa

View Project
Similar Project

Interiors and Furniture work.

View Project
Similar Project

Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators for various projects in Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.