Project Duration
Stipulated Date of Commencement April 21 2018
Stipulated Date of Completion /
Likely Date of Completion
May 20 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,968,800.00
Awarded for ₹ 2,701,502.43

Project highlights

Providing roofing on terrace of Block A of EDC House to prevent water leakages and to protect the interior work of GSIDC office at 7th & 8th floor.

 
Gallery Image
Contractors
M/s.Vishal Engineering, Kolhapur
Gallery Image
Consultants
M/s.Intrinsic Classic
 
Similar Projects

See Similar Projects

Similar Project

External painting of buildings for IFFI 2014.

View Project
Similar Project

Refurbishment of Maquinez Palace, Maquinez Palace Annexe, Heritage Building (ESG), Panaji, Goa

View Project
Similar Project

External Electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.