Project Duration
Stipulated Date of Commencement January 23 2019
Stipulated Date of Completion /
Likely Date of Completion
April 22 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,509,004.70
Awarded for ₹ 1,260,000.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of a 5 Passenger lift at the premises.

 
Gallery Image
Contractors
M/s.Omega Elevators
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Painting and other ancillary works along major internal roads of Panaji city

View Project
Similar Project

Construction of Office Building for Directorate of Accounts at Porvorim, Goa

View Project
Similar Project

Lab furniture work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.