Project Duration
Stipulated Date of Commencement
May 13 2016
Stipulated Date of Completion /
Likely Date of Completion December 09 2016
Likely Date of Completion December 09 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,662,180.00
Awarded for
₹ 24,679,996.75
Project highlights
Interior work for commerical tax dept at margao and curchorem
Contractors
M/s. Swastik Space Craft LLP
Consultants
M/s. Ameet Sukhthankar
See Similar Projects
Construction of Laboratories for Agricultural Department at Ella Old Goa and Margao.
View Project
Maintenance of building under DFDA, Bambolim,Goa – SH-Maintenance contract of 180 KVA DG set installed at DFDA, Bambolim for three years.
View Project
Interior Works for FDA block at Margao