Project Duration
Stipulated Date of Commencement
September 14 2017
Stipulated Date of Completion /
Likely Date of Completion September 13 2018
Likely Date of Completion September 13 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,807,658.00
Awarded for
₹ 21,072,072.85
Project highlights
construcction of hall with 300 capacity for socio & cultural events and provison of anganwadi at lower ground floor