Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion September 07 2019
Likely Date of Completion September 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,817,056.68
Awarded for
₹ 15,736,138.28
Project highlights
Structural roofing work for IT Hub
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. KICONS Ltd.