Project Duration
Stipulated Date of Commencement September 10 2014
Stipulated Date of Completion /
Likely Date of Completion
August 01 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,882,348.32
Awarded for ₹ 3,805,873.00

Project highlights

work consists of providing fire suppression system for UPS and server room.

 
Gallery Image
Contractors
M/s.Douse Fire System Pvt. Ltd.,
Gallery Image
Consultants
M/s. KICONS Ltd.,
 
Similar Projects

See Similar Projects

Similar Project

Additional works for new SCERT building at Porvorim, Goa

View Project
Similar Project

Lab furniture work

View Project
Similar Project

Supply of trees, grass, grass covers & allied material for landscaping works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.