Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,420,363.00
Awarded for
₹ 8,520,325.00
Contractors
M/s. Lit Homes
Consultants
M/s. Effective Architectural Services
See Similar Projects
Package I (Village Panchayat Agassaim, Village Panchayat Neura).
View Project
Soft landscaping.
View Project
Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction