Project Duration
Stipulated Date of Commencement
May 24 2018
Stipulated Date of Completion /
Likely Date of Completion July 23 2018
Likely Date of Completion July 23 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,053,934.00
Awarded for
₹ 5,529,555.00
Project highlights
Providing AC to new building for Directorate of Education
Contractors
M/s. Nikhil Comforts
Consultants
M/s. Datta Kare Associates