Project Duration
Stipulated Date of Commencement
February 24 2014
Stipulated Date of Completion /
Likely Date of Completion April 23 2014
Likely Date of Completion April 23 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,179,260.00
Awarded for
₹ 3,887,000.00
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)