Project Duration
Stipulated Date of Commencement
May 30 2018
Stipulated Date of Completion /
Likely Date of Completion June 05 2018
Likely Date of Completion June 05 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,500.00
Awarded for
₹ 27,500.00
Contractors
M/s. Sharavi Constructions Pvt. Ltd.
Consultants
M/s. Effective Architectural Services