Project Duration
Stipulated Date of Commencement January 25 2014
Stipulated Date of Completion /
Likely Date of Completion
March 24 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,79,96,453.11
Awarded for ₹ 31,090,851.72
 
Gallery Image
Contractors
M/s. ASP Water and Power Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction

View Project
Similar Project

Landscape and external development works at Multiplex Courtyard.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Audio, Video and CCTV Surveillance System for District Library at Navelim, Margao.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.