Project Duration
Stipulated Date of Commencement January 20 2011
Stipulated Date of Completion /
Likely Date of Completion
July 19 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,548,704.00
Awarded for ₹ 11,883,785.00
 
Gallery Image
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works

View Project
Similar Project

Refurbishment of Maquinez Palace, Maquinezuinez Palace Annex and Old GMC Building for IFFI 2017 -Electrical Works.

View Project
Similar Project

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.