Project Duration
Stipulated Date of Commencement
August 14 2010
Stipulated Date of Completion /
Likely Date of Completion December 13 2010
Likely Date of Completion December 13 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,300,928.00
Awarded for
₹ 16,920,811.16
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Effective Architectural Services