Project Duration
Stipulated Date of Commencement
August 14 2010
Stipulated Date of Completion /
Likely Date of Completion December 13 2010
Likely Date of Completion December 13 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,300,928.00
Awarded for
₹ 16,920,811.16
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Effective Architectural Services
See Similar Projects
Fire Fighting Works
View Project
CPOE switches
View Project
Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators for various projects in Goa.
View Project