Project Duration
Stipulated Date of Commencement
October 05 2009
Stipulated Date of Completion /
Likely Date of Completion March 04 2010
Likely Date of Completion March 04 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,450,000.00
Awarded for
₹ 2,570,000.00
Contractors
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services