Project Duration
Stipulated Date of Commencement
December 23 2019
Stipulated Date of Completion /
Likely Date of Completion January 22 2020
Likely Date of Completion January 22 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 316,440.00
Awarded for
₹ 346,332.00
Project highlights
Fire safety and exit signages work
Contractors
M/s. Geeta Automation Technologies
Consultants
In-house (GSIDC)