Project Duration
Stipulated Date of Commencement January 17 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,02,563.00
Awarded for ₹ 2,983,810.00

Project highlights

Landscaping works

 
Gallery Image
Contractors
M/s. Vrindavan Agricultural Services
Gallery Image
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Development plan of site of Shree Mahalasa Devi temple at Verna-Phase II.

View Project
Similar Project

Establishing Infrastructure for the Organic Waste Management Facility at Patto, Panaji – Balance works

View Project
Similar Project

Maintenance of building under DFDA, Bambolim,Goa – SH-Maintenance contract of 180 KVA DG set installed at DFDA, Bambolim for three years.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.