Project Duration
Stipulated Date of Commencement
December 07 2018
Stipulated Date of Completion /
Likely Date of Completion April 16 2019
Likely Date of Completion April 16 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,003,936.00
Awarded for
₹ 8,936,969.00
Project highlights
Interior work
Contractors
M/s. Creation Interiors
Consultants
M/s. FP Project Management
See Similar Projects
– Additional Miscellaneous work.
View Project
Construction of new building for Directorate of Education at DIET Complex at Porvorim – Electrical works
View Project
Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction – Electrical works at St. Inez.
View Project