Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion March 21 2014
Likely Date of Completion March 21 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 613,577.00
Awarded for
₹ 638,500.00
Contractors
M/s. RICOH India Ltd.,
Consultants
In-house (GSIDC)
See Similar Projects
Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works
View Project
Facilitation Services, Installation, Testing & Commissioning of Theatre equipments.
View Project
Supply of Adult folding wheel chair for pilgrims for Exposition 2014 at Old Goa.
View Project