Project Duration
Stipulated Date of Commencement October 27 2014
Stipulated Date of Completion /
Likely Date of Completion
November 26 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,569,033.00
Awarded for ₹ 1,722,777.57

Project highlights

Providing of additional loose Interior, signages etc.

 
Gallery Image
Contractors
M/s. Harshada Trading Company
Gallery Image
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Gas piping work.

View Project
Similar Project

Ancillary works at Divja Circle to Dona Paula Jetty and ESG complex, Panaji, Goa for IFFI 2012.

View Project
Similar Project

Construction of High Court Complex at Penha de Franca, Porvorim.Civil, Plumbing, Electrical, HVAC, Lift and Firefighting works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.