Project Duration
Stipulated Date of Commencement February 23 2013
Stipulated Date of Completion /
Likely Date of Completion
August 22 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,832,122.81
Awarded for ₹ 6,839,446.96
 
Gallery Image
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Gas piping work.

View Project
Similar Project

Providing 11 KV transformer substation for release of electrical connection to the office premises of Commercial Tax Office, Ponda .

View Project
Similar Project

Desktop scanners

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.