Project Duration
Stipulated Date of Commencement
December 06 2010
Stipulated Date of Completion /
Likely Date of Completion January 05 2011
Likely Date of Completion January 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,571,330.00
Awarded for
₹ 8,292,525.00
Contractors
M/s. Reconnoitre Systems
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
See Similar Projects
Landscaping work.
View Project
Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction
View Project
Beautification of lake at Curtorim (Ralloitollem).
View Project