Project Duration
Stipulated Date of Commencement
December 04 2010
Stipulated Date of Completion /
Likely Date of Completion February 03 2011
Likely Date of Completion February 03 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 74,60,421.00
Awarded for
₹ 72,37,840.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.