Project Duration
Stipulated Date of Commencement
April 19 2013
Stipulated Date of Completion /
Likely Date of Completion June 18 2013
Likely Date of Completion June 18 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,655,969.78
Awarded for
₹ 2,467,550.00
Project highlights
Additional Electrical works required for completing of project
Contractors
M/s. Arken Solutions Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.