Project Duration
Stipulated Date of Commencement
May 21 2012
Stipulated Date of Completion /
Likely Date of Completion September 20 2012
Likely Date of Completion September 20 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,737,760.00
Awarded for
₹ 16,462,076.00
Project highlights
Audio-Video works for Ravindra Bhavan
Contractors
M/s. AGC Networks Limited
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.