Project Duration
Stipulated Date of Commencement
April 26 2011
Stipulated Date of Completion /
Likely Date of Completion October 25 2011
Likely Date of Completion October 25 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,373,990.00
Awarded for
₹ 12,323,666.60
Project highlights
Fire fighting works for Ravidra Bhavan
Contractors
M/s. Fire Remedy Systems
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.