Project Duration
Stipulated Date of Commencement November 12 2014
Stipulated Date of Completion /
Likely Date of Completion
January 11 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 13,681,148.00
Awarded for ₹ 16,543,756.55

Project highlights

Construction of Washrooms at Old Goa for Exposition 2014

 
Gallery Image
Contractors
M/s. R.S. Lawande
Gallery Image
Consultants
M/s. LKS India Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Carpentry work.

View Project
Similar Project

Construction of Library Building at Margao.

View Project
Similar Project

Development of Service road and Site Development at Mont Boa Vista for Exposition 2014 – Electrical works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.