Project Duration
Stipulated Date of Commencement
November 12 2014
Stipulated Date of Completion /
Likely Date of Completion January 11 2015
Likely Date of Completion January 11 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,681,148.00
Awarded for
₹ 16,543,756.55
Project highlights
Construction of Washrooms at Old Goa for Exposition 2014
Contractors
M/s. R.S. Lawande
Consultants
M/s. LKS India Pvt. Ltd.
See Similar Projects
Carpentry work.
View Project
Construction of Library Building at Margao.
View Project
Development of Service road and Site Development at Mont Boa Vista for Exposition 2014 – Electrical works
View Project