Project Duration
Stipulated Date of Commencement December 29 2016
Stipulated Date of Completion /
Likely Date of Completion
March 28 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,627,249.00
Awarded for ₹ 8,005,852.89

Project highlights

Beautification with soft and hard landscaping work

 
Gallery Image
Contractors
M/s. Gurudatt Gardeners & Developers
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Audio, Video and CCTV Surveillance System for District Library at Navelim, Margao.

View Project
Similar Project

Balance beautification works from Miramar Circle to Betim Ferry Ramp

View Project
Similar Project

Additional furniture items.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.