Project Duration
Stipulated Date of Commencement
November 07 2017
Stipulated Date of Completion /
Likely Date of Completion November 25 2017
Likely Date of Completion November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 827,427.00
Awarded for
₹ 848,095.00
Project highlights
The scope of work includes replacement of non-functional CFL light fixtures with the LED light fixtures, LED street light fixtures, repairs of street lights in the courtyard of ESG premises.
Contractors
M/S. Volton Engineering India Pvt Ltd
Consultants
M/S.Vaishali Pednekar Associates