Project Duration
Stipulated Date of Commencement
October 01 2013
Stipulated Date of Completion /
Likely Date of Completion October 30 2013
Likely Date of Completion October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,326,816.00
Awarded for
₹ 10,499,999.00
Project highlights
The scope of work involves dismantling of the existing nonfunctional VRV System and installation of the new VRV Air-Conditioning System at Maquinez Palace and Maquinez Palace Annex Building.
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment