Project Duration
Stipulated Date of Commencement
September 13 2013
Stipulated Date of Completion /
Likely Date of Completion September 27 2013
Likely Date of Completion September 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 461,294.00
Awarded for
₹ 461,294.00
Project highlights
Refurbishment work of Maquiniz Palace complex prior to IFFI 2013.
Contractors
M/s. Pest Control (India) Pvt. Ltd.
Consultants
M/s. UCJ Architecture & Environment
See Similar Projects
Construction of new building for SCERT at Porvorim, Goa
View Project
Solid Waste Management during St. Francis Xavier Exposition 2014 – 2015 at Old Goa including sweeping, door to door colleciton, soiling and segregation, transportation and bailing of Municipal waste.
View Project
Erection, Testing & Commissioning of Air Conditioned Hangar at Dayanand Bandodkar Football Ground, Campal, Panaji for IFFI 2013.
View Project





