Likely Date of Completion October 27 2007
Project highlights
The Restoration & refurbishment of FDA building and Maquinez palace was planned to house offices for Directorate of Film Festivals, Press Information Bureau, Media Centre, Offices of the Entertainment Society of Goa, Viewing rooms, Auditorium and associated infrastructure, Presentation room, Art Gallery, Film Museum, Print Unit and Storage, Guest Rooms, Associated functions of registration, conferences, briefing room, lounge, support facilities in toilets, services, etc.
Contractors
Consultants
Sub Works
This project involved 9 sub works. The details of the same available below
Interiors and Furniture work.
Likely Date of Completion November 07 2007
Contractors
Consultants
EPABX system.
Likely Date of Completion November 12 2007
Contractors
Consultants
Facilitation Services, Installation, Testing & Commissioning of Theatre equipments.
Likely Date of Completion November 07 2007
Contractors
Consultants
Electrical works.
Likely Date of Completion October 31 2007
Contractors
Consultants
Theatre System (non-proprietory).
Likely Date of Completion November 03 2007
Contractors
Consultants
Construction of RCC sump and pumping system.
Likely Date of Completion November 29 2008
Contractors
Consultants
HVAC works.
Likely Date of Completion November 07 2007
Contractors
Consultants
Fire Hydrant / Alarm System.
Likely Date of Completion November 12 2007
Contractors
Consultants
Additional miscellaneous works
Likely Date of Completion September 07 2009
Contractors
Consultants
See Similar Projects
Supply of “Shot Blasted Interlocking Pavers.”
View Project
Supply, Installation, Testing & Commissioning of CCTV system at Goa Medical College.
View Project
Construction of Sewage Treatment Plant at Sanquelim, Goa – Connection of houses to sewer lines.
View Project