Project Duration
Stipulated Date of Commencement November 14 2017
Stipulated Date of Completion /
Likely Date of Completion
December 14 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,019,832.00
Awarded for ₹ 8,371,107.76

Project highlights

Painting of buildings for IFFI 2017

 
Gallery Image
Contractors
M/s.Rakesh Kambli
Gallery Image
Consultants
M/s.Vaishali Pednekar & Associates
 