Project Duration
Stipulated Date of Commencement October 28 2016
Stipulated Date of Completion /
Likely Date of Completion
January 27 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 39,893,986.00
Awarded for ₹ 36,930,164.00

Project highlights

Soft and hard landscaping work in the gardans and along DB Road

 
Gallery Image
Contractors
M/s. Green Mek Hortitek Pvt. Ltd.
Gallery Image
Consultants
M/s. Shobha Bhopatkar
 
Similar Projects

See Similar Projects

Similar Project

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

View Project
Similar Project

Construction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa – Civil, electrification & land development work.

View Project
Similar Project

Replacement of failed cables and supply, installation of new fixtures, spares for the streetlights along D.B. Marg from Kadamba Bus stand to Miramar Circle (IFFI 2018)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.