Project Duration
Stipulated Date of Commencement
November 08 2012
Stipulated Date of Completion /
Likely Date of Completion December 07 2012
Likely Date of Completion December 07 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,027,233.00
Awarded for
₹ 8,917,189.96
Project highlights
Repairs to certain electrical components in Kala Academy in view of IFFI 2012.
Contractors
M/s. Power & Instrumentation (Guj) Ltd.
Consultants
M/s. Nilesh Salkar Associates
See Similar Projects
Readymade furniture works
View Project
Construction of building at Patto with provision for Gas insulated substation Panaji Phase I
View Project
External development works.
View Project





