Project Duration
Stipulated Date of Commencement
December 12 2012
Stipulated Date of Completion /
Likely Date of Completion January 07 2013
Likely Date of Completion January 07 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,312,379.00
Awarded for
₹ 27,265,350.00
Project highlights
Widening of various roads by constructing retaining walls, providing full grout and hotmixing from Banyan tree to Pausada Hotel upto Fat Fish Restaurant, and from Fat Fish Restaurant to Baga Bridge in Calangute constituency. Approxitmate length of roads- 3.70 km
Contractors
M/s.Ritesh Developers Pvt. Ltd
Consultants
In-house (GSIDC)