Project Duration
Stipulated Date of Commencement
June 20 2021
Stipulated Date of Completion /
Likely Date of Completion October 17 2021
Likely Date of Completion October 17 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,658,751.00
Awarded for
₹ 11,264,964.00
Project highlights
Electrical wiring, SITC of electrical substation at three existing sheds
1) Organic waste management facility behind Heera petrol pump patto.
2) Waste Management facility opposite LIC building at Patto.
3) Material recovery facility at St. Inez in panaji.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Construction of Sanskruti Bhavans for Department of Tribal Welfare at Baradi, Velim, Salcete.
View Project
Solid Waste Management during St. Francis Xavier Exposition 2014 – 2015 at Old Goa including sweeping, door to door colleciton, soiling and segregation, transportation and bailing of Municipal waste.
View Project
Maintenance of building under DFDA, Bambolim,Goa – SH-Maintenance contract of 180 KVA DG set installed at DFDA, Bambolim for three years.
View Project