Project Duration
Stipulated Date of Commencement December 21 2014
Stipulated Date of Completion /
Likely Date of Completion
August 20 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,526,608.00
Awarded for ₹ 13,721,642.06

Project highlights

• Multipurpose Playground of approximately 5600 m2 area with doob grass.
• Paved jogging track of length approximately 310 m and 3.0 m width, illuminated by LED lighting
• Drainage system to drain out rain water
• Plantation of trees and shrubs
• Volleyball court (Clay base)
• Toilet block and office room
• 2 nos of underground tank of 13000 liters capacity each
• Paved Parking space and footpath
• Compound wall with one no of 4m wide gate and 2 nos of 2m wide gates on other side.

 
Gallery Image
Contractors
M/s. Prasad Enterprises
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/ Upgradation & Maintainence of Government schools in the State of Goa – Pernem Taluka – Package II (GPMS Pernem, Office of the ADEI Pernem)

View Project
Similar Project

Interior, Electrical and Lift work

View Project
Similar Project

Reconstruction of Government High School at Betoda, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.