Project Duration
Stipulated Date of Commencement
October 05 2018
Stipulated Date of Completion /
Likely Date of Completion March 04 2019
Likely Date of Completion March 04 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,439,186.00
Awarded for
₹ 19,999,179.84
Project highlights
External Development works
Contractors
M/s.Decent Decorators,
Consultants
M/s. F P Project Management Pvt. Ltd.
See Similar Projects
Repairs/upgradation & maintenance of Government primary Schools in the state of Goa -Civil, plumbing and electrical works-package A – GPS Ghadiwada GPS Deulmol Sirvoi, GPS Deulamol Markarnem and GPS Pontemol.