Project Duration
Stipulated Date of Commencement March 01 2014
Stipulated Date of Completion /
Likely Date of Completion
May 01 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,857,508.00
Awarded for ₹ 4,404,197.00

Project highlights

Construction of water storage tank for fire safety purpose

 
Gallery Image
Contractors
M/s. K. V. Gaonkar,
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Medical Gas & Other Connected works for OTs.

View Project
Similar Project

STP & ETP works

View Project
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem Goa and Major Civil works sanctioned under NRHM – ROP 2012-13.: Phase I: Repair and upgradation works of existing community health centre under NRHM

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.