Project Duration
Stipulated Date of Commencement
August 15 2018
Stipulated Date of Completion /
Likely Date of Completion August 16 2021
Likely Date of Completion August 16 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,689,890.00
Awarded for
₹ 6,285,481.00
Project highlights
Maintenance work
Contractors
M/s. Hi-Tech Engineering Works
Consultants
In-house (GSIDC)