Project Duration
Stipulated Date of Commencement
October 18 2019
Stipulated Date of Completion /
Likely Date of Completion October 17 2022
Likely Date of Completion October 17 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,646,350.00
Awarded for
₹ 3,644,379.00
Project highlights
Carriage of water
Contractors
M/s. Pedro Gomes
Consultants
In-house (GSIDC)