Project Duration
Stipulated Date of Commencement
November 12 2013
Stipulated Date of Completion /
Likely Date of Completion November 11 2014
Likely Date of Completion November 11 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,025,750.00
Awarded for
₹ 2,044,000.00
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa
View Project
Procurement of Equipment for Burns unit (New Ward 118) Dept. of Plastic Surgery, GMC, Bambolim Goa – SH: SITC of Flash Autoclave
View Project