Project Duration
Stipulated Date of Commencement
March 18 2019
Stipulated Date of Completion /
Likely Date of Completion May 17 2019
Likely Date of Completion May 17 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 468,019.00
Awarded for
₹ 464,915.00
Project highlights
Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
In-house (GSIDC)