Project Duration
Stipulated Date of Commencement March 18 2019
Stipulated Date of Completion /
Likely Date of Completion
May 17 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 468,019.00
Awarded for ₹ 464,915.00

Project highlights

Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.

 
Gallery Image
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of 13 Passenger with Stretcher Lifts at TB and Chest Disease Hospital, St.Inez – Goa

View Project
Similar Project

Upgradation of Morgue situated at T. B. Sanatorium, Monte Hill, Margao -Civil, Plumbing & Electrical work.

View Project
Similar Project

Reconstruction / Upgradation of Primary Health Centre at Sanquelim, Goa -Civil & Plumbing work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.