Project Duration
Stipulated Date of Commencement
June 06 2019
Stipulated Date of Completion /
Likely Date of Completion May 07 2019
Likely Date of Completion May 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 87,305.00
Awarded for
₹ 95,700.00
Project highlights
Supply, Installation, Testing and Commissioning of Audio Power Amplifiers for Lecture Halls 4, 5 & 6 at Goa Medical College
Contractors
M/s. ACE-TECH,
Consultants
In-house (GSIDC)
See Similar Projects
External electrical work
View Project
Supply, Installation, Testing and Commissioning of Echo machines.
View Project
DG work.
View Project





