Project Duration
Stipulated Date of Commencement
December 16 2018
Stipulated Date of Completion /
Likely Date of Completion January 15 2019
Likely Date of Completion January 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 190,942.00
Awarded for
₹ 199,479.00
Project highlights
SITC of Cold storage unit for Microbiology Department at Goa Medical College.